Late 1993 
Ford/Mazda agreed on expanded cooperative relationship
June 1994 
Feasibility team formed
August 1994 
Announced JV truck manufacturing project in Thailand
July 1995 
Joint Venture feasibility study submitted to BOI
August 1995 
Thai joint-venture office formed in Hiroshima
 October 1995 
BOI approved assembly project
 January 1996 
Temporary Bangkok administration office opened
February 1996 
AAT's ground-breaking ceremony at Eastern Seaboard Industrial Estate, Rayong Province
July 1996 
AAT's first trainee group sent to Mazda Motor Corporation in Hiroshima, Japan First steel column erected
 February 1997 
Equipment installation commenced
May 1997 
Administration office opened
October 1997 
Final stages of installation and start of pilot production
May 1998 
Production Job # 1
July 1998 
Production start-up ceremony
December 1998 
First export shipment ceremony
July 1999 
First KD export ceremony
September 1999 
Received ISO 9002 certificate
January 2000 
Start of car production

 