Late 1993
|
Ford/Mazda
agreed on expanded cooperative relationship |
|
June 1994
|
Feasibility team formed
|
|
August 1994
|
Announced JV truck
manufacturing project in Thailand |
|
July 1995
|
Joint Venture feasibility
study submitted to BOI |
|
August 1995
|
Thai joint-venture
office formed in Hiroshima |
|
October 1995
|
BOI approved assembly
project |
|
January 1996
|
Temporary Bangkok administration
office opened |
|
February 1996
|
AAT's ground-breaking
ceremony at Eastern Seaboard Industrial Estate, Rayong Province |
|
July 1996
|
AAT's first trainee
group sent to Mazda Motor Corporation in Hiroshima, Japan First steel
column erected |
|
February 1997
|
Equipment installation
commenced |
|
May 1997
|
Administration office
opened |
|
October 1997
|
Final stages of installation
and start of pilot production |
|
May 1998
|
Production Job # 1 |
|
July 1998
|
Production start-up
ceremony |
|
December 1998
|
First export shipment
ceremony |
|
July 1999
|
First KD export ceremony |
|
September 1999
|
Received ISO 9002 certificate |
|
January 2000
|
Start of
car production |
|
|
 |